Jerseyville owns and operates a 2 MGD Potable Water Treatment Plant and a 2 MGD / 6 MGD Max. Wastewater Treatment Plant along with the water distribution (approx. 100 miles of mains of various sizes and materials) and wastewater collection (approx. 65 miles of gravity mains and 15 miles of forced mains) systems.

The Water Treatment Plant is located just south of Nutwood, IL. Water is pumped from one of three operational wells located about ¾ of a mile west of the treatment plant. The plant was constructed in 1960’s and has minor upgrades over time. In 1993 work was authorized and funded by a matching grant to add the third well and to extend the well heads above the 1993 flood level. A new pump house was constructed and generator added to supply power in the event of a power outage and to reduce the draw for power in the event of a peak power event. This allows for a reduced power rate in normal power periods allowing for reduced treatment and pumping costs.

Along with the well improvements added pumping capacity from the treatment plant to Jerseyville was included with these upgrades along with the replacement of critical outdated and undersized water mains along 2/3’s of the transmission line. Completion of the parallel transmission main – approximately 4 miles of 16” main remains to be installed to complete this upgrade. The communication system that coordinates the treatment plant with the distribution system was updated with the plant upgrades. Most of the remaining plant is original. General maintenance and repairs have allowed for some of the operating valves and controls to be updated and replaced.

The Wastewater Treatment Plant is a new state of the art Activated Sludge – SBR – Sequential Batch Reactor Facility that was completed in 2014 with the final chemical feed systems put online in 2015. The need to construct/reconstruct this plant was due to the added need for plant capacity. The plant that was in service was designed to be expanded, however the IEPA would no longer permit a plant using the RBC technology in place. The only real option was to proceed with the reconstruction of the facility with a treatment process that would be permitted.

In November of 2011, the City of Jerseyville completed financing requirements and authorized the replacement of the RBC treatment facility. Much of the new facility was able to be constructed while the existing facility remained in service. By the middle of 2014 wastewater was diverted into the new facility and sections of the new plant were phased into service as areas were completed.

Jerseyville’s Water and Sewer Department is staffed by a Supervisor, 3 Water Plant Operators, 3 Wastewater Plant Operators, 4 maintenance workers and a meter reader. Office support including billing is supplied by the City Clerk’s Office.

2017 Water Report
2016 Water Report
2015 Water Report
2014 Water Report
2013 Water Report

Water Shut Off Dates

January 26th, February 23rd, March 29th, April 26th, May 25th, June 28th, July 26th, August 29th, September 27th, October 25th, November 28th, December 27th

Payments

Direct Debit Form

All fees associated with billing and or services should be paid at the

City of Jerseyville Water & Sewer Offices
115 East Prairie Street
Jerseyville, IL 62052
(618) 498-3211

Type of Payment accepted: Cash or Check

Drive up window is available 8:00am – 4:30pm
After Hours/Night Drop available on the corner of building next to drive-up window.

An additional option for payment of your water bill is direct debit. Please fill out the form to begin the process. Please use Adobe Reader or Acrobat Pro. After you have completed the form, save the pdf and email it to forms@jerseyville-il.us.

Rates and Fees

Water Deposit
i.Water contracts must be filled out and submitted in person at City Hall –– 115 Prairie St. Jerseyville, IL 62052
ii. Owner – $75.00
iii.Renter – $100.00

Delinquent Fees
i.Bills paid after 8:30 a.m. on the 11th of every month or the next business day if it falls on a weekend, will have a 10% late fee applied to the total amount of the bill
ii.Bills not paid after 8:30 a.m. on the 25th of every month will have a $25.00 fee applied to the total amount of the bill

Water Only or Water Portion of Water and Sewer Charge Inside the City Limits
i.First 1500 gallons – $20.00 (Total is the Sum of WA-Water based on Consumption; EPA ––Testing Fees; WI –– Water Capital Improvement Fee)
ii.Over 1500 gallons, per 100 gallons – $0.80

Sewer Portion of Water and Sewer Charge Inside the City Limits
i.First 1500 gallons – $28.00 (Total is the Sum of SW–– Sewer Replacement; SI –– Sewer/Capital Improvement; Sewer based on Water Consumption Fee)
ii.Over 1500 gallons, per 100 gallons – $0.80
iii.Sewer Service Only –– Flat Fee – $40.00 (Total is the Sum of SW –– Sewer Replacement; SI ––Sewer/Capital Improvement; Sewer Flat Rate Fee)

Water Only or Water Portion of Water and Sewer Charge Outside the City Limits
i.First 1500 gallons – $36.75 (Total is the Sum of WA-Water based on Consumption; EPA ––Testing Fees; WI –– Water Capital Improvement Fee)
ii.Over 1500 gallons, per 100 gallons – $0.95

Sewer Portion of Water and Sewer Charge Outside the City Limits
i.First 1500 gallons – $43.25 (Total is the Sum of SW–– Sewer Replacement; SI –– Sewer/Capital Improvement; Sewer based on Water Consumption Fee)
ii.Over 1500 gallons, per 100 gallons – $0.95
iii.Sewer Service Only –– Flat Fee – $40.00 (Total is the Sum of SW –– Sewer Replacement; SI ––Sewer/Capital Improvement; Sewer Flat Rate Fee)

Bulk Tank Water Charge
i.Per 1000 gallons – $10.00

Sprinkler System
i.Annual Fee charged to anyone who installs a sprinkler system based on the gross square footage of the building.
ii.Under 1000 square ft (minimum charge) – $20.00
iii.1000 to 2500 – $30.00
iv.2501 to 4000 – $40.00
v.4001 to 6000 – $50.00
vi.6001 to 8000 – $ 60.00
vii.8001 to 10,000 – $70.00
viii.10,001 to 15,000 – $80.00
xi.15,001 to 20,000 – $90.00
x.20,001 to 100,000 – $100.00
xi.Over 100,000 – $250.00

Tap Fees
Existing Water Tap Fee (ReTap)
1. All fees are 50% of the Tap Fees listed below

New Water Tap inside the City Limits
1. One (1) inch line – $2000.00
2. Two (2) inch line –– $2800.00

New Water tap outside the City Limits
1. For all sizes (1-2 inch) lines – $3000.00
2. New subdivision developers shall pay $2800.00 plus $75.00 per lot

Sewer taps four (4) and six (6) inch, inside city limits, sight previously on sewer mains (ReTap)
1. All fees are 50% of the Tap Fees listed below

Sewer taps four (4) and six (6) inch, inside city limits, sight not previously on sewer mains
1. $3200.00

New Sewer taps –– Site not previously on City Sewer Mains –– Outside City Limits –– CUSTOMER FURNISHES ALL MATERIALS
1. $4400.00

Contractors and Developers will be charged an inspection fee of $75.00 each for Water and Sewer Lines

Please use the link below for the informational packet from Illinois American Water that was distributed during the Public Informational Meeting on the Potential Sale of the Water and Sewer Department of the City of Jerseyville the evening of Monday, October 9, 2017. Hard copies are also available for viewing at City Hall (115 E. Prairie St.)

Informational Packet from Illinois American Water

Jerseyville_Executive Summary_10092017Final_Part1

Jerseyville_Executive Summary_10092017Final_Part2

Jerseyville_Executive Summary_10092017Final_Part3

Buried No Longer

Drinking-Water-Final

Wastewater-Final

InfrastructureReportCard_ASCE2017_Overview

Informational Packet From Citizens Advisory Committee

Presentation for Public Meeting 100917 53 Slides_Part1

Presentation for Public Meeting 100917 53 Slides_Part2

City of Jerseyville Illinois
115 East Prairie Street
Jerseyville Illinois 62052
P:618.498.3312
F:618.498.4122
HOURS OF OPERATION 8:00 a.m. to 4:30 p.m.
Top