Demolition Requirements

Demolition Requirements

  1. All utilities must be disconnected before demolition can begin.
  2. A final inspection is required when demolition is complete to ensure both water & sewer is capped.

Applications are not complete until payment of fees associated with said application has been received.
No work should begin until the application has been completed.

All questions and/or concerns should be directed to:

City of Jerseyville
Department of Building and Zoning
Jeff Soer
Director of Building and Zoning
115 East Prairie Street
Jerseyville, IL 62052
P: (618) 498-3312
E: jeffsoer@jerseyville-il.us